City of Santa Fe offices and facilities will close early on Friday, April 3 in observance of a spring holiday.
Learn more here.

Disclaimer: The information in the Orange Barrel report is compiled based on the best available information and is subject to change without notice.

This page was updated on Friday, March 27, 2026, at 9:56 am


 

PROJECT ONGOING AS SCHEDULED

Contractor: Hasse Contracting Company

Location: 237 Don Gaspar Ave

Description: Sidewalk, curb, and gutter improvements. The project is scheduled to begin on 3/23/2026 and end on 4/03/2026. The project will require a full road closure on the segment of Don Gaspar Ave from W. DeVargas Ave to W. Alameda St.

Traffic control will be in place. Motorists are encouraged to seek alternate routes when possible and to allow extra time when traveling through the area.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov  

 

PROJECT ONGOING AS SCHEDULED

Contractor: Davenport Construction Management

Location: Shelby St. at E. Alameda  

Description: Pedestrian Bridge over the Santa Fe River demolition. Work begins 2/17/2026, and completion is to be determined. No major traffic interruptions are expected.  

Contact: Scott Overlie, saoverlie@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: Sub Surface Contracting

Location: 507 Camino Cabra

Description: Sub Surface will be doing a new Sewer Lateral Tap on 507 Camino Cabra Road, which will be closed from 8 a.m. to 5 p.m. All detours and advanced warning signs will be in place. The detour route will be Camino Cabra to Camino De La Luz to Camino Delora to Camino San Acacio, and the same route in the opposite direction. This will start 2/9/2026 through 3/9/2026. Please expect delays. The road closure is for the safety of workers and the public. Thank you for the understanding.

Contact: Albert Chavez wachavez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: GM Emulsion

Location: Airport Rd

Description: Road rehabilitation project between Cerrillos Rd and NM-599. Initial work includes ADA curb ramp replacements, sidewalk and concrete improvements, and Asphalt paving as weather allows. Construction is scheduled to begin on 2/23/26 and is anticipated to continue through the end of May 2026, weather and field conditions permitting. Traffic control shall be in place throughout the project. Motorists are encouraged to seek alternate routes when possible and to allow extra time when traveling through the area.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: GM Emulsion

Location: 2530 W. Alameda St.

Description: Arroyo structure outfall repairs. Work is anticipated to be completed in four months. Traffic Control Signage will be in place. Proceed with caution.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: EMCO of Santa Fe, LLC.

Location: Calle Angelina from 1504 to 1562.  

Description: Calle Angelina Road has been recently repaved. The project requires minor pavement striping to be scheduled within two weeks, which is expected to conclude by the end of the week, weather permitting. Please proceed with caution.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: GM Emulsion

Location: Tierra Contenta Trail, between Sweeney Elementary and Ortiz Middle School.

Description: Construction of a new ten-foot-wide bike and pedestrian trail, erosion control, and stormwater treatments began in August. The new trail will connect Avenida Contenta to South Meadows Rd via an extension. Starting the week of April 6th, Lucia Lane will be closed to allow construction of the trail crossing. Work is expected to last through April 17th. The project is expected to be completed in the fall of 2026.   

Contact:  Kody Keelin kwkeelin@santafenm.gov or Romella Glorioso-Moss rsglorioso-moss@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: EMCO of Santa Fe: Project Ongoing, But Delayed updates

Location: Agua Fria & South Meadows  

Description: This project addresses failing traffic signals at Agua Fria and South Meadows due to changing land use in the area. Improvements include a new traffic signal, intersection upgrades, bike lanes, ADA-compliant sidewalks, and added turning lanes to enhance safety, reduce congestion, and achieve NMDOT Level of Service (LOS) A.

Crews will be removing two PNM power poles and transferring fiber optic cable the week of March 30th - April 3rd. During this work, the roadway will remain open with lane shifts and flagging operations in place. Brief delays are expected, especially during mast arm installation. Motorists are advised to use caution in the work zone.  

We appreciate the community’s patience as we complete this long-awaited project, which will improve safety, mobility, and accessibility for all.

Contact: Kody Keelin kwkeelin@santafenm.gov or Romella Glorioso-Moss
rsglorioso-moss@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: Daniel’s Landscaping & Construction

Location: Buckman ATV/MX Track Prak, End of Chili Line Trail, and north of 599

Description: Installation of a water tank and pump house. No traffic flow disturbances, but the park will be closed. Work begins 11/17/2025 and is estimated to finish 03/06/2026.

Contact: Carlos Saiz, crsaiz@santafenm.gov, 505-795-2556

 

PROJECT ONGOING AS SCHEDULED

Contractor: SF Brown, Inc.  

Description: Zia Station Public Infrastructure project.  

  • Speed limit on Galisteo Rd. reduced to 25 mph between Zia Rd and Calle Luminoso

  • LEFT turns from Galisteo to Zia Rd. are prohibited.

  • Westbound Zia Rd. still reduced to a single lane between St. Francis Dr. and Candelero

  • Construction vehicles will occupy and stage activities from and in the closed WB Zia outside lane. Please use caution.

  • Sidewalk on the south side of Zia is open from Vela to St. Francis

  • Sidewalk on the north side of Zia has been removed and is closed to all pedestrian traffic – please use the sidewalk on the south side of Zia.

  • WATCH FOR TRUCKS/EQUIPMENT ENTERING AND EXITING ZIA ROAD TO/FROM ZIA FLATS APARTMENT PROJECT ON NORTH SIDE OF ZIA RD.

Contact: Merritt Brown, merritt@sfbrown.com, Ryan Gomez, rmgomez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: Sub Surface Contractor

Location: Camino Del Monte Sol and Camino Santander

Description: Sub Surface is contracted by the City Water Dept. To install new water lines from Garcia St. to Camino Del Monte Sol, down to Camino Santander. There will be road closures during the day as work is performed. Follow detour signs as directed. Residents will have access in and out of their homes, and emergency services will have access if needed. Work duration will continue on January 5th for a few months. They will also be working on Camino Corrales this week, which will be closed to through traffic from Garcia Street to Old Santa Fe Trail during the day. Follow Detour signs as needed.

Contact: Albert Chavez wachavez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: True North Builders LLC  

Location: 206 Mckenzie

Description: 206 Mckenzie is closed due to a whole remodel of the building on Mckenzie. There is no room for all the workers on site. The road is closed for equipment, staging area, and stucco work on the building. All detours are in place, and traffic control is up. Due to break-ins on the property, this closure has helped with these issues. Once the weather warms up, the stucco will be completed. The project completion date is August.  

Contact: Cody North buildnorth@gmail.com  Ryan Gomez rmgomez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: Fuquay Inc.

Location: W. San Francisco St and N. Guadalupe St.

Description: Fuquay Inc. will begin a sewer main relining project on W. San Francisco St. and N. Guadalupe St.

Daytime Work – Beginning March 6.  

W. San Francisco St. will be closed daily from 8 a.m. to 5 p.m. Crews will move the closure west along W. San Francisco St., starting at N. Guadalupe St. and progressing toward Paseo de Peralta. Each work zone will cover approximately 750 ft.  

Night Work – March 17 through March 26. Night work will take place from 9 p.m. to 9 a.m. During these hours, N. Guadalupe St. will be closed.  

Motorists and pedestrians are encouraged to plan alternate routes and allow additional travel time in the area.  

All traffic control and detours are in place. Please follow detours.  

Contact: Luke Gray, lgray@santafenm.gov Ryan Gomez, rmgomez@santafenm.gov

 

NEW PROJECT

Contractor: Utilities Quality Performance

Location: 1604 Agua Fria St

Description: Utilities Quality Performance will have Agua Fria St. closed starting 3/30/26 through 4/6/26 for sewer work. All traffic going East on Agua Fria St will detour right onto Osage Ave, and westbound traffic will detour through Potencia St to Cerrillos Rd. All traffic control will be set up, and detours will be in place. Please follow detours and expect delays. Seek an alternate route.  

Contact: Ryan Gomez rmgomez@santafenm.gov

 

NEW PROJECT

Contractor: Blueline Construction

Location: Beckner Rd & Cerrillos Rd

Description: Blueline Construction will have Beckner Rd closed at Cerrillos Rd, and Beckner Rd at Wellness Way closed. They will be doing right-of-way work requiring a road closure. All traffic control will be in place, and all detours will be set up. Please seek an alternate route. The detour route will be down Wellness Way. Beckner Rd will be closed starting 4/6/26.  

Contact: Ryan Gomez rmgomez@santafenm.gov  

 

NEW PROJECT

Contractor: Daniel’s Construction & Landscaping NEW

Location: Fifth Street to Llano

Description: Daniel’s will be cleaning the arroyo between Fifth Street and Llano starting 3/30/2026. Work is anticipated to take one week with no impact on traffic.

Contact: jgallegos1@santafenm.gov

 

NEW PROJECT

Contractor: PNM New Mexico  

Location: Cottonwood Drive

Description: PNM will relocate three power poles and install one new steel pole. Traffic control will be in place for lane shifts. Small delays are expected.  

Contact: kwkeelin@santafenm.gov