April 8, 2019
Orange Barrel Report April 8, 2019

Orange Barrel Report for the week of April 8, 2019

New This Week:

Agua Fria: Concrete work on ADA ramps; replacement of curb and gutter; Osage Ave. to St. Francis Dr. April 8, 2019 to June 3, 2019; 8:00am – 7:00pm (Weather permitting) Single lane roadway with flaggers and some full closures.

Montezuma St.: Replace curb and gutter; new sidewalk and ADA curb ramps; April 5, 2019 to May 31, 2019; Shoulder work with Flagging. 

Cerrillos Rd. at Chama: March 28.2019 to April 12, 2019; 8:30 am to 4:30 pm;  West bound Cerrillos Rd turn bay going north on to St. Michael’ Dr. will be impacted, delays on Cerrillos are to be expected.

Galisteo at De Vargas: March 28, 2019 to April 30, 2019; 8:30 am to 4:30 pm; shoulder work,  north bound turn bay to De Vargas will be closed    

Cerro Gordo and Camino Gonzales; March 28, 2019 to April 4, 2019; 8:30 am to 4:30 pm; Flagging will be used in all four directions

On-going:

Johnson St.: Concrete work on ADA ramps; curb and milling and paving of roadway; Guadalupe to Grant Ave; April 3, 2019 to May 6, 2019; 7:00 am to 7:00 pm; Single lane roadway with flaggers and some full closures.

Galisteo Rd; Milling and paving between Rodeo Road and Zia road March 27, 2019 to April 12, 2019 (weather permitting); 7:00am – 7:00pm; the road will be reduced to one lane with a Flagger operation in place in some areas. Expect Delays; if possible, please seek an alternate route.

Calle Lorca: Concrete work at the intersection of Calle Lorca and San Mateo March 18, 2019 to April 26, 2019 (Weather permitting); 7:00am – 7:00pm;The roadway will be reduced to a single lane with no turn bays on San Mateo. Expect delays; if possible, please seek an alternate route

Siler Road: Water Main replacement between Cerrillos Rd and Agua Fria St;  October 1, 2018 to end of May 2019; 8:30 am – 4:30 pm (Weather Permitting); lane shift .   

South Meadows: Installation of turn lanes; Agua Fria St. to the 599 round-about; March 11, to April 30.2019; 8:30 am – 4:30 pm; traffic controls will be up for the duration of the project; shoulder work with times of lane shifts.

Old Santa Fe Trail: Installation of fiber optics lines between Coronado and Camino Pinones; February 28, 2019 to April 30, 2019;   8:30 am to 4:30 pm; Flagger operation 

Acequia Madre: Installation of fiber optics lines between Garcia St and Calle Corvo; February 28, 2019 to April 28, 2019;  8:30 am to 4:30 pm; Flagger operation 

Cerrillos Rd: Installation of aerial cable; San Felipe to Siler Rd.; November 2018 to Completion Date; 8:30 am- 4:30 pm; Shadow truck setup

Cerrillos Rd: Installation of aerial cable; St. Michael’s Dr. and 3rd St.; March 18,2019 to May 18, 2019; 8:00am to 4:30 pm. Single lane closure

Don Gaspar Ave: Installation of aerial cable; E. Coronado Rd. and W. Cordova Rd. March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.: Shoulder work

Old Santa Fe Trail: Installation of aerial cable; Camino Pinones east bound to the curve; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.: Shoulder work

Jemez Rd.: Installation of aerial cable; Airport Rd. to Agua Fria St.; 8:00 am - 4:30 pm; March 13, 2019 to May 19, 2019. flagger operation

Cerrillos Rd.; Installation of aerial cable; Vegas Verdes and Richards Ave.; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; shadow truck setup.

Old Pecos Trail and Old Santa Fe Trail: Installation of aerial cable ; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; shadow truck setup

Coronado: Installation of aerial cable; Don Gasper and Old Pecos Trail; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; shoulder setup.

Arroyo Tenorio: Installation of aerial cable; Don Gasper and Old Pecos Trail; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; flagger setup.

Up Coming:

Avenida de las Campanas - Installation of aerial cable; April 15, 2019 to April 19, 2019; 8:30 am to 4:30 pm; Shoulder work.

 