On-going:

Cerrillos Rd: Installation of fiber optic cable on power poles; Siler Rd. to Vegas Verdes; April 18, 2019 to May 20, 2019; 8:30 am to 4:30 pm; Lane shift and turn lane closed east bound 

Avenida de las Campanas: Concrete work on bridge deck; April 22, 2019 to June 3, 2019; 8:00 am – 7:00 pm (Weather permitting); Lane shift.

Agua Fria: Concrete work on ADA ramps; replacement of curb and gutter; Osage Ave. to St. Francis Dr. April 8, 2019 to June 3, 2019; 8:00am – 7:00pm (Weather permitting);Single lane roadway with flaggers and some full closures.

Montezuma St.: Replace curb and gutter; new sidewalk and ADA curb ramps; April 5, 2019 to May 31, 2019; Shoulder work with Flagging.

Galisteo at De Vargas: March 28, 2019 to April 30, 2019; 8:30 am to 4:30 pm; shoulder work,  north bound turn bay to De Vargas will be closed.    

Johnson St.: Concrete work on ADA ramps; curb and milling and paving of roadway; Guadalupe to Grant Ave; April 3, 2019 to May 6, 2019; 7:00 am to 7:00 pm; Single lane roadway with flaggers and some full closures.

Galisteo Rd; Stripping of roadway; Rodeo Road and Zia road March 27, 2019 to May 6, 2019 (weather permitting); 7:00am – 7:00pm; the road will be reduced to one lane with a Flagger operation in place in some areas. Expect Delays; if possible, please seek an alternate route.

Calle Lorca: Stripping of roadway; of Calle Lorca and San Mateo March 18, 2019 to May 6, 2019 (Weather permitting); 7:00am – 7:00pm; The roadway will be reduced to a single lane with no turn bays on San Mateo. Expect delays; if possible, please seek an alternate route.

Siler Road: Water Main replacement between Cerrillos Rd and Agua Fria St; October 1, 2018 to end of May 2019; 8:30 am – 4:30 pm (Weather Permitting); lane shift.   

South Meadows: Installation of turn lanes; Agua Fria St. to the 599 round-about.  March 11, to April 30.2019; 8:30 am – 4:30 pm; traffic controls will be up for the duration of the project; shoulder work with times of lane shifts. 

Old Santa Fe Trail: Installation of fiber optics lines between Coronado and Camino Pinones; February 28, 2019 to May 30, 2019;   8:30 am to 4:30 pm; Flagger operation. 

Acequia Madre: Installation of fiber optics lines between Garcia St and Calle Corvo; February 28, 2019 to May 28, 2019;  8:30 am to 4:30 pm; Flagger operation. 

Cerrillos Rd: Installation of aerial cable; San Felipe to Siler Rd.; November 2018 to Completion Date; 8:30 am- 4:30 pm; Shadow truck setup.

Cerrillos Rd: Installation of aerial cable; St. Michael’s Dr. and 3rd St.; March 18,2019 to May 18, 2019; 8:00am to 4:30 pm. Single lane closure.

CerrillosRd:  Installation of aerial cable; south on Camino Carlos Rey then west on Siringo Rd.; April 11, 3019 to April 26, 2019;Flagman setup when needed.

Don Gaspar Ave: Installation of aerial cable; E. Coronado Rd. and W. Cordova Rd. March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.: Shoulder work. 

Old Santa Fe Trail: Installation of aerial cable; Camino Pinones east bound to the curve; March 18, 2019 to May 28, 2019; 8:00 am to 4:30 pm.: Shoulder work.

Jemez Rd.: Installation of aerial cable; Airport Rd. to Agua Fria St.; 8:00 am - 4:30 pm; March 13, 2019 to May 19, 2019. Flagger operation.

Cerrillos Rd.; Installation of aerial cable; Vegas Verdes and Richards Ave.; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; Shadow truck setup.

Old Pecos Trail and Old Santa Fe Trail: Installation of aerial cable ; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; shadow truck setup.

Coronado: Installation of aerial cable; Don Gasper and Old Pecos Trail; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; shoulder setup.

Arroyo Tenorio: Installation of aerial cable; Don Gasper and Old Pecos Trail; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; March 18, 2019 to May 18, 2019; 8:00 am to 4:30 pm.; flagger setup.

  